MEIL BV PKG 11 RPL
MEIL BV Pkg 11 Roadways Private Limited

MEIL BV PKG 11 RPL

Project Highlights

Scope of Work

Client

Length in Km

Pavement Classification

Role /Type Details Type
EPC Contractor M/s. Megha Engineering & Infrastructures Limited
Independent Engineer M/s Dhruv Consultancy Services Ltd., in JV with M/s G Eng Advisory Services Pvt Ltd & association with M/s Kaius Consulting Pvt Lt.
Agreement Date 1st May 2023
Appointed Date 12th Feb 2024
Maintenance Period 15 Years after commencing
COD Construction Period 24 Months (730 days) from Appointed Date
Project Cost Rs. 854.71 Crores
Structures Scope Details
Sl. No Type of Structure Scope (In Nos)
1 Box Culverts /Structures 65
2 VUP 02
3 LVUP 07
4 Pipe Culverts 08
5 Interchange (Double Trumpet) 02
6 Minor Bridges 12
7 Major Bridges 03
Total - Structures 105
8 Tunnel(M) 300 M