Scope of Work
Client
Length in Km
Pavement Classification
| Role /Type | Details Type |
| EPC Contractor | M/s. Megha Engineering & Infrastructures Limited |
| Independent Engineer | M/s Dhruv Consultancy Services Ltd., in JV with M/s G Eng Advisory Services Pvt Ltd & association with M/s Kaius Consulting Pvt Lt. |
| Agreement Date | 1st May 2023 |
| Appointed Date | 12th Feb 2024 |
| Maintenance Period | 15 Years after commencing |
| COD Construction Period | 24 Months (730 days) from Appointed Date |
| Project Cost | Rs. 854.71 Crores |
| Structures Scope Details | ||
| Sl. No | Type of Structure | Scope (In Nos) |
| 1 | Box Culverts /Structures | 65 |
| 2 | VUP | 02 |
| 3 | LVUP | 07 |
| 4 | Pipe Culverts | 08 |
| 5 | Interchange (Double Trumpet) | 02 |
| 6 | Minor Bridges | 12 |
| 7 | Major Bridges | 03 |
| Total - Structures | 105 | |
| 8 | Tunnel(M) | 300 M |